Work is continuing on the Quadrangle redevelopment, with good progress being made, including the start of the development of the plaza area.

Ahead of the hard-landscaping work on the plaza, a drainage system has been installed. Once completed, this will create a more natural and fluid link with Imperial Gardens.

The internal works are also nearing completion with many areas now being snagged, including the office space on Level 4. The ground-floor reception desk has been installed along with the entrance turnstiles, while external steps are beginning to be formed next to the reception area. Glass balustrades are also now in place and tiling is underway in the external areas.

In the basement, the changing areas are progressing, with the showers being installed and tiling in progress. Now that Savills has moved into their new space, refurbishment is progressing well on their previous home and cables have been installed which will provide upgraded power to the building.

Interest from prospective tenants also continues and with the marketing suite now finished, this helps to highlight what an attractive and inspiring workplace Quadrangle will be.